Latest News
As reported by public relations of Pars Oil and Gas Company (POGC), director of Kish gas field development plan, Abdullah Mehrabi, pointed out to the start of the longest marine pipe-laying operations on Thursday, July 23, between Kish island shore and Garzeh region in southern province of Hormozgan, saying that the project includes one 32-inch pip... More...
Saturday, July 25, 2020
ASSALUYEH – following operational plans to maintain production from South Pars gas field, extensive operations started to acidize offshore wells of phase 8. In order to increase gas recovery coefficient and make the production period longer and more stable from South Pars offshore platforms, the wells of productive platforms in the block o... More...
Tuesday, June 9, 2020
ASALOYEH (POGC) – Iran’s Pars oil and gas Company has officially started operations to install the jacket of South Pars Phase 11 platform in the Persian Gulf. Iranian President Hassan Rouhani ordered start of the jacket installation in the Block-B reservoir of Phase 11 via video conference. In the live broadcast, Iranian Minister of... More...
Thursday, May 21, 2020
The operation to load the first jacket of phase 11, has started today, April 29, at industrial yard of NSQ company in Qeshm island. The jacket belongs to platform B of the phase 11 which is called SPD11B. It is going to load out and transport to its location on South Pars gas field by carrier barge LB90, Rasoul Fallahnejad was quoted by public re... More...
Thursday, April 30, 2020
Deputy head of South Pars phase 19, Hossein Azimi, announced that single point mooring (SPM) shipment arrived at Pars port wharf on Saturday April 26. Referring to use of SPM system as one of common ways to transport gas condensate to tankers, Hossein Azimi said that such system is restrained by chain and anchors that are hammered into the seabed... More...
Sunday, April 26, 2020
ASSALUYEH – the last platform of phase 14 started its operation with the production capacity of 500 million cubic feet (equivalent to 14 million cubic meters) of sour gas a day. Offshore facilities of phase 14 was completed on Thursday, March 19, by putting the last platform of this plan into operation. Now it is generating 2 billion cubic ... More...
Friday, March 20, 2020
TEHRAN – Iranian companies have matured during South Pars development projects. They are currently doing well on $5 billion projects, managing director of Pars Oil and Gas Company (POGC), Mohammad Meshkinfam, announced. Speaking on the state TV, Meshkinfam noted that magnitude activities have been performed by Iranian companies so that... More...
Sunday, March 8, 2020
ASSALUYEH – the last deck of phase 13 was successfully installed in its location. The fourth or the last deck belonging to phase 13 called 13C, while observing all safety requirements, was lifted and installed on its jacket today March 7, by the installer vessel HL5000, director of phase 13, Payyam Motamed, was quoted by public relations a... More...
Saturday, March 7, 2020
BUSHEHR - The operation to load out two decks of phase 13 ended at SADRA today February 9. The two decks, each weighing about 2500 tons, have made 98 percent progress which were simultaneously loaded on the carrier vessel called FLB124 at manufacturing yard of Iran marine industrial company with the method of Push Pull, director of phase 13, Pa... More...
Monday, February 10, 2020
ASSALUYEH – the last offshore deck of south pars phase 14 was installed successfully. The last deck of phase 14, which is called 14D, was lifted and installed on its jacket on Saturday, February 1, public relations reported. Constructed by Iran marine industrial company in the yard of SADRA, SPD14D was loaded on carrier vessel FLB124 an... More...
Friday, February 7, 2020
Page 5 of 82First   2  3  4  [5]  6  Last